Question: Question 7 of 50 Which two tools do scrum teams use to ensure that the team is always working on the highest-priority items? the
Question 7 of 50 Which two tools do scrum teams use to ensure that the team is always working on the highest-priority items? the product backlog the project release plan the sprint backlog the project requirements the epic board