Question: Which two tools do scrum teams use to ensure that the team is always working on the highest - priority items? the project requirements the

Which two tools do scrum teams use to ensure that the team is always working on the highest-priority items?
the project requirements
the product backlog
the epic board
the sprint backlog
the project release plan
 Which two tools do scrum teams use to ensure that the

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!