QUESTION 7 The Cyclone project team has started gathering information necessary to develop a project network. The results of their meeting are found in the following table:
7.1 Draw the project network of this project. Compute the early and late activity times and slack times. Identify the critical path. (10)
7.2 Suppose activity D had a duration length of 10 days instead of 13 days what happens to the project completion time.
7.3 Draw a scheduled bar chart using the earliest due date scheduling techniques. (4)
7.4 Why do you use the earliest due date