Question: Question 8 4 pts Given this information about activity 3-4: ES = 10, EF = 15, LS-16, and LF = 21, we can determine that

Question 8 4 pts Given this information about
Question 8 4 pts Given this information about activity 3-4: ES = 10, EF = 15, LS-16, and LF = 21, we can determine that the amount of slack associated with the activity is: 6. O 1. O 11. 5. 4 pts Question 9