Question: Question 8 A project's AC is $113,000. Its EV is $85,000, and the BAC is $135,000. It's no longer feasible to finish within the BAC,
Question 8
A project's AC is $113,000. Its EV is $85,000, and the BAC is $135,000. It's no longer feasible to finish within the BAC, so you forecast a new EAC of $145,000. What's the TCPI, based on the EAC?
Select one:
a. 2.27
b. 1.56
Question 9
Which items are inputs to the estimate costs process?
Select one or more:
a. Policy for cost contingencies
b. Risk register
c. Organizational process assets
d. Variance thresholds
e. Enterprise environmental factors
- Which elements are inputs of the determine budget process?
Select one or more:
a. Cost baseline
b. Cost monitoring and reporting tools
c. Banking interest rates
d. Benefits management plan
e. Vendor contracts
f. Scope baseline
g. Basis of estimates
h. Project funding requirements
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
