Question: Question 8 of 9 . The program manager for the transportation directorate requested that the COR submit a request to change the contract. The change
Question of
The program manager for the transportation directorate requested that the COR submit a request to change the contract. The change is an increase in quantity of truck tires costing $ each, under a fixed price tire contract for tires. Choose the best answer regarding the scope of this requirement.
Increases in quantity are not a scope issue.
The contractor can be forced by the Contracting Officer to accept this cardinal change.
This increase may not be within the scope of this tire contract.
The COR can direct the contractor by change order to increase production numbers only if money is available.