Question: The program manager for the transportation directorate requested that the cor submit a request to change the contract. The change is an increase in quantity

The program manager for the transportation directorate requested that the cor submit a request to change the contract. The change is an increase in quantity of 1000 truck tires costing $225 each, under a fixed price tire contract for 500 tires. Choose the best answer regarding the scope of this requirement