Question: Question 8 On a project the project manager should strive for a Quality Level that Represents the least cost to the project. Is the highest
- Question 8
On a project the project manager should strive for a "Quality Level" that
-
Represents the least cost to the project.
-
Is the highest level possible
-
Exceeds the specified requirements of the project.
-
Is as close to the project objectives as possible
-
- Question 9
Which one of the following is the best way to manage stakeholders?
-
Keeping them informed throughout the project
-
Ensuring they don't get to meet outside of work
-
Meeting all of them when a milestone is ready
-
Sending them gifts
-