Question: Question 8 There are five activities in making one toy: cutting, sewing, stuffing, assembling, and packaging. The activities have to be carried out in this
Question 8
There are five activities in making one toy: cutting, sewing, stuffing, assembling, and packaging. The activities have to be carried out in this order. The processing time of each activity is given below:
| Activity | Processing time (minutes per toy) |
| Cutting | 15 |
| Sewing | 8 |
| Stuffing | 8 |
| Assembling | 10 |
| Packaging | 5 |
Demand rate is 4 toys per hour. Currently we have worker A in charge of cutting and sewing, worker B in charge of stuffing, and worker C in charge of assembling and packaging. Which of the following strategies will increase the process capacity by balancing the line ?
Group of answer choices
Adding one additional worker to cutting.
Adding two additional workers to assembling.
Moving sewing to worker B.
Moving packaging to worker A.