Question: There are five activities in making one toy: cutting, sewing, stuffing, assembling, and packaging. The activities have to be carried out in this order. The
There are five activities in making one toy: cutting, sewing, stuffing, assembling, and packaging. The activities have to be carried out in this order. The processing time of each activity is given below:
| Activity | Processing time (minutes per toy) |
| Cutting | 10 |
| Sewing | 10 |
| Stuffing | 5 |
| Assembling | 5 |
| Packaging | 25 |
Demand rate is 4 toys per hour. Currently we have worker A in charge of cutting, worker B in charge of sewing and stuffing, and worker C in charge of assembling and packaging. Which of the following strategies will increase the process capacity by balancing the line?
A. Adding one additional worker to assembling.
B. Adding two additional workers to assembling.
C. Moving packaging to worker A.
D. Moving assembling to worker B.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock