Question: Question 9 1 pts (9) Consider three mutually exclusive projects: Project A, Project B and Project C. The NPV of these projects are given as:

Question 9 1 pts (9) Consider three mutually exclusive projects: Project A, Project B and Project C. The NPV of these projects are given as: Project A 37,000 Project B 28,000 Project C 14.000 NPV The project costs are not the same. Which of the following is all three projects will be rejected. only Project A will be chosen. all three projects will be chosen. only Project will be chosen. both Project A and B will be chosen Question 10 (10) The NPV of a project will_ _ if the cost of capital increases. increase o not change decrease