Question: Consider three mutually exclusive projects: Project A, Project B, and Project C. The NPV of these projects are given as: project A project B Project
Consider three mutually exclusive projects: Project A, Project B, and Project C. The NPV of these projects are given as:
| project A | project B | Project C | |
| NPV | 37,000 | 28,000 | 14,000 |
The project costs are not the same. which of the following is correct?
A) Only project C will be chosen
B) All three projects will be chosen
C) Only project A will be chosen
D) All three projects will be rejected