Question: Question 9 4 pts Program Evaluation and Review Technique ( PERT ) uses these three time estimates shortest, longest, average deterministic, stochastic, functional earliest, latest,
Question
pts
Program Evaluation and Review Technique PERT uses these three time estimates
shortest, longest, average
deterministic, stochastic, functional
earliest, latest, slack
optimistic, pessimistic, most likely