9. Given the following highway rerouting project, Immediate Activity Predecessor {months} A: Schedule crew 4 B: Schedule equipment 6 C: Plan new mute A 2 D: Costs meet budget? B 6 E: Inform public C,E 3 F: Put em signs C,E 3 G: Begin rerouting 13,13 5 21. Draw the network. I). Find the E55, L35. and slacks. c. Find the critical path. d. If the project has a l Illyear deadline for reopen ing, shmld we consider crashing some activi- tiesiExplain