Question: Given the following highway rerouting project, (a) Draw the network. (b) Find the ESs, LSs, and slacks. (c) Find the critical path. (d) If the
Given the following highway rerouting project,
.png)
(a) Draw the network.
(b) Find the ESs, LSs, and slacks.
(c) Find the critical path.
(d) If the project has a 1 1/2-year deadline for reopening, should we consider crashing some activities?Explain.
Immediatc Activity Time Predecessor (months) Activity A: Schedule crew B: Schedule equipment C: Plan new route D: Costs meet budget? E: Inform public F: Put out signs G: Begin rerouting 4 C, B C, B D, E
Step by Step Solution
3.31 Rating (154 Votes )
There are 3 Steps involved in it
a and b c The critical path is B D G as shown in Figure 94 ... View full answer