Question: Question 9 As a project manager, you re identifying task dependencies. Task B cannot finish until Task A is complete the tasks operate at the
Question
As a project manager, youre identifying task dependencies. Task B cannot finish until Task A is completethe tasks operate at the same time. Which type of dependency does this situation represent?
point
Finish to Start FS
Finish to Finish FF
Start to Start SS
Start to Finish SF
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
