Question: Question 9 As a project manager, you re identifying task dependencies. Task B cannot finish until Task A is complete the tasks operate at the

Question 9
As a project manager, youre identifying task dependencies. Task B cannot finish until Task A is completethe tasks operate at the same time. Which type of dependency does this situation represent?
1 point
Finish to Start (FS)
Finish to Finish (FF)
Start to Start (SS)
Start to Finish (SF)

Step by Step Solution