Question: Question: Based on the following network diagram and table, find which activities will be crashed and identify the crashing sequence. 5 6 O 01 A

Question: Based on the following network diagram

Question: Based on the following network diagram and table, find which activities will be crashed and identify the crashing sequence. 5 6 O 01 A B Start 4 End G 8 10 D 25 F Activity Duration Crashed Cost (USD) Crashed Cost (USD) A 5 3 5,000 6,000 B 6 4 6,000 7,500 9 6 8,000 9,500 D 10 5 8,500 12,000 E 8 4 7,000 8,500 25,000 F 25 14 18,000 G 4 3 3,000 3,500