Question: . Question c32 The following Data gives for each activity of a project its duration and corresponding resource requirements as well as total availability of

. Question c32 The following Data gives for each

.

Question c32 The following Data gives for each activity of a project its duration and corresponding resource requirements as well as total availability of each type of resource : Activity Duration Resources required (days) Machines Men 1-2 72 20 1-3 7 2 20 2-3 8 3 30 2-4 6 4 30 3-6 9 2 20 4-5 3 2 20 5-6 5 2. 20 Minimum available resources : Machines Men 4 40 (i) Draw the network, compute earliest occurrence time and latest occurrence time for each event, the total float for each activity and identify the critical path assuming that there are no resource constraints. (ii) Under the given resource constraints find out the minimum duration N X Z

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!