Question: QUESTION 39 Consider the following work breakdown structure: Activity B D E F G H Start Node 1 1 2 2 3 4 5 Finish

QUESTION 39 Consider the following work breakdown
QUESTION 39 Consider the following work breakdown structure: Activity B D E F G H Start Node 1 1 2 2 3 4 5 Finish Node 2 3 4 5 5 6 6 7 Duration Estimate (Days) Optimistic Most Likely Pessimistic 9 15 21 13 21 23 6 9 18 23 35 47 19 26 27 23 29 41 14 26 2. 5 8 20 8 6 What are the estimated slack times (in weeks) for activities A-H? 1:5; 0; 3; 10; 0; 0;3; 2 10; 0; 1;5; 0; 5; 0; 10 5: 1:5; 0; 15; 5; 3; 0 0;5; 15; 0; 5; 15; 0; 0

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!