Question: Consider the following work breakdown structure: Pessimistic 68 32 78 Activity B D E F G H Start Node 1 1 2 3 4 4

Consider the following work breakdown structure:

Consider the following work breakdown structure: Pessimistic 68 32 78 Activity B D E F G H Start Node 1 1 2 3 4 4 5 6 Finish Node 2 3 4 4 5 6 7 7 Duration (days) Optimistic Most Likely 62 65 28 30 62 70 32 41 55 62 38 62 66 32 35 65 32 43 74 39 What is the probability that this project will be completed within 270 days? (Keep 3 decimal places)