Question: Question content area left Part 1 Task time estimates for the modification of an assembly line at Jim Goodale's Carbondale, Illinois, factory are as follows:

Question content area left
Part 1
Task time estimates for the modification of an assembly line at Jim Goodale's Carbondale, Illinois, factory are as follows:
Activity
Time
(in hours)
Immediate Predecessor(s)
A
7.0
long dash
B
7.2
long dash
C
5.0
A
D
7.0
B, C
E
5.1
B, C
F
7.7
D
G
5.0
E, F