Question: Chapter 3 , Question 7 , part a: Task time estimates for the modification of an assembly line at Jim Goodale's Carbondale, Illinois, factory are
Chapter Question part a:
Task time estimates for the modification of an assembly line at Jim Goodale's Carbondale, Illinois, factory are as follows:
tableACTIVITY TIME IN HOURStableIMMEDIATEPREDECESSORSABCADB CEB CFDGE F
a Draw the project network using AON.
b Identify the critical path.
c What is the expected project length?
d Draw a Gantt chart for the project.
An AOA network is needed for this question
None of the above
A An AOA network is needed for this question
B None of the above
Solutions CD & E are provided in the picture