Question: Question No 2: [10 Marks] Consider the figure given above please fill all activity nodes with ES, EF, LS, LF and Total Float. Find the
![Question No 2: [10 Marks] Consider the figure](https://dsd5zvtm8ll6.cloudfront.net/si.experts.images/questions/2024/12/67600908c4955_016676009083d0cb.jpg)
Question No 2: [10 Marks] Consider the figure given above please fill all activity nodes with ES, EF, LS, LF and Total Float. Find the Critical and Non-Critical Path Link by Drawing Arrow between Activity Links.
10 3 E 5 10 6 C 8 D