Question: Question One (10 Marks): Given the below table, develop project network schedule. Complete the forward and backward (ES, EF, LS, LF), compute activity slack, and

Question One (10 Marks): Given the below table,

Question One (10 Marks): Given the below table, develop project network schedule. Complete the forward and backward (ES, EF, LS, LF), compute activity slack, and identify the critical path. ID A B C D E F G H I L Predecessor None A A B,C 0,8 0,CE 5,0 GH, LH G,J,K Time (weeks) 1 5 3 2 4 2 8 3 5 3 2