Question: QUESTION ONE Activity Immediate predecessors Expected Completion Time (week) Optimistic Most likely pessimistic A - 2 4 6 B - 3 5 6 C -

QUESTION ONE

Activity

Immediate predecessors

Expected Completion Time (week)

Optimistic

Most likely

pessimistic

A

-

2

4

6

B

-

3

5

6

C

-

2

3

4

D

B

4

6

10

E

A,B

3

4

6

F

B

1

2

3

G

F,C

2

5

7

H

G

2

4

5

I

F

1

3

4

J

I,D

2

3

8

K

J

1

1

1

L

E,K

4

8

10

Show the activity schedule and slack for each activity.