Question: Activity Immediate predecessors Expected Completion Time (week) Optimistic Most likely pessimistic A - 2 4 6 B - 3 5 6 C - 2 3
| Activity | Immediate predecessors | Expected Completion Time (week) | ||
| Optimistic | Most likely | pessimistic | ||
|
|
|
|
|
|
| A | - | 2 | 4 | 6 |
| B | - | 3 | 5 | 6 |
| C | - | 2 | 3 | 4 |
| D | B | 4 | 6 | 10 |
| E | A,B | 3 | 4 | 6 |
| F | B | 1 | 2 | 3 |
| G | F,C | 2 | 5 | 7 |
| H | G | 2 | 4 | 5 |
| I | F | 1 | 3 | 4 |
| J | I,D | 2 | 3 | 8 |
| K | J | 1 | 1 | 1 |
| L | E,K | 4 | 8 | 10 |
- Calculate the estimated time for each activity.
- Show the network for this project using activity-on-arrow method.
- What are the critical path activities and the expected project completion time?
Show the activity schedule and slack for each activity.