Question: Question: The following table shows three time estimate ( Optimistic , Pessimistic, and Most likely ) of a project with 5 activities:The following table shows

Question: The following table shows three time estimate (Optimistic, Pessimistic, and Most likely) of a project with 5 activities:The following table shows three time estimate (Optimistic, Pessimistic, and Most likely) of a project with 5 activities:ActivityO (Optimistic time)M (Most likely time)P (Pessimistic time)Immediate PredecessorA136-B345AC246BD6910A, CE2610DConduct a PERT analysis and find the critical path of the project.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!