Question: The following table shows three time estimate ( Optimistic , Pessimistic, and Most likely ) of a project with 5 activities: ActivityO ( Optimistic time

The following table shows three time estimate (Optimistic, Pessimistic, and Most likely) of a project with 5 activities:ActivityO (Optimistic time)M (Most likely time)P (Pessimistic time)Immediate PredecessorA136-B345AC246BD6910A, CE2610DConduct a PERT analysis and find the critical path of the project.The following table shows three time estimate (Optimistic, Pessimistic, and Most likely) of a project with 5 activities:ActivityO (Optimistic time)M (Most likely time)P (Pessimistic time)Immediate PredecessorA136-B345AC246BD6910A, CE2610DConduct a PERT analysis and find the critical path of the project.The following table shows three time estimate (Optimistic, Pessimistic, and Most likely) of a project with 5 activities:ActivityO (Optimistic time)M (Most likely time)P (Pessimistic time)Immediate PredecessorA136-B345AC246BD6910A, CE2610DConduct a PERT analysis and find the critica
1
2 points
The following table shows three time estimate (Optimistic, Pessimistic, and Most likely) of a project with 5 activities:
\table[[Activity,O (Optimistic time),M(Most likely time),P(Pessimistic time),Immediate Predecessor],[1,3,6,-],[B,3,4,5,A],[C,2,4,6,B],[D,6,9,10,A, C],[E,2,6,10,D]]
Conduct a PERT analysis and find the critical path of the project.l path of the project.
 The following table shows three time estimate (Optimistic, Pessimistic, and Most

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!