Question: The following table shows three time estimate (Optimistic, Pessimistic, and Most likely) of a project with 5 activities: Activity O (Optimistic time) M (Most likely

The following table shows three time estimate (Optimistic, Pessimistic, and Most likely) of a project with 5 activities:

Activity

O (Optimistic time)

M (Most likely time)

P (Pessimistic time)

Immediate Predecessor

A

1

3

6

-

B

3

4

5

A

C

2

4

6

B

D

6

9

10

A, C

E

2

6

10

D

Conduct a PERT analysis and find the critical path of the project.