Question: The following table shows three time estimate (Optimistic, Pessimistic, and Most likely) of a project with 5 activities: Activity O (Optimistic time) M (Most likely
The following table shows three time estimate (Optimistic, Pessimistic, and Most likely) of a project with 5 activities:
Activity | O (Optimistic time) | M (Most likely time) | P (Pessimistic time) | Immediate Predecessor |
A | 1 | 3 | 6 | - |
B | 3 | 4 | 5 | A |
C | 2 | 4 | 6 | B |
D | 6 | 9 | 10 | A, C |
E | 2 | 6 | 10 | D |
Conduct a PERT analysis and find the critical path of the project.