Question: Question ( 10 marks ) Using the table provided below, calculate the late start of activity C. You are required to show all your work

Question ( 10 marks )

Using the table provided below, calculate the late start of activity C. You are required to show all your work (including a critical path diagram) and provide an explanation of each step in your process to support your answer.

Activity Name Predecessor Duration Duration
A None 5
B A 2
C A 6
D A 3
E D 1