Question: QUESTION THREE [25] Using the network diagram below: A 10 15 D ES LSEF LF ES LSEF LF F 18 B 9 ES LSEF LF

QUESTION THREE [25] Using the network diagram
QUESTION THREE [25] Using the network diagram below: A 10 15 D ES LSEF LF ES LSEF LF F 18 B 9 ES LSEF LF ES LSEF LF G 10 E 17 ES LSEF LF ES LSEF LF + 13 ES LSEF LF 3.1. (5) (10) (10) Identify the Critical Path. Calculate the Early Start; Late Start; Early Finish & Late Finish for all activities. Compute the 'slack" time for each activity. 3.2. 3.3