Question: QUESTION: When you crash the project the maximum amount possible, the new project cost (include crash costs) is $____. The following table provides the information

QUESTION: When you crash the project the maximum amount possible, the new project cost (include crash costs) is $____.
The following table provides the information necessary to construct a project network, along with project crash data. Normal conditions Crash conditions Activity Predecessor Time (weeks) Cost ($/week) Weeks available to crash Cost ($/week) - 1 20 50 12 40 - 24 50 4 50 3 - 14 50 7 70 4 1 10 4 5 3 11 506 30 1 2 |Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts