Question: QUESTIONFOUR A project has the following characteristics: ( a ) Construct the network ( b ) Find the critical path and variance for each event

QUESTIONFOUR
A project has the following characteristics:
(a) Construct the network
(b) Find the critical path and variance for each event
(c) Find the project duration at 95% probability.QUESTION FIVE
(a) A self - service store employs one cashier at its counter. Nine customers arrive on an
average every 5 minutes while the cashier can serve 10 customers in 5 minutes. Assuming
Poisson distribution for arrival rate and exponential distribution for service time, find
i. Average number of customers in the system
ii. Average number of customers in the queue or average queue length
iii. Average time a customer spends in the system
iv. Average time a customer waits before being served
(b) A tax consulting firm has 3 counters in its office to receive people who have problems
concerning their income, wealth and sales taxes. On the average 48 persons arrive in an 8
-hour day. Each tax adviser spends 15 minutes on an average on an arrival. If the arrivals
are Poissonly distributed and service times are according to exponential distribution, find
i. The probability of there being no customer in the system
ii. The average number of customers in the system
iii. Average number of customers waiting to be served
iv. Average time a customer spends in the system
v. Average waiting time for a customer
 QUESTIONFOUR A project has the following characteristics: (a) Construct the network

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!