Question: Questions 1 - 6 Use the following problem statement to answer questions 1 - 6 . The project network below shows activity times ( in

Questions 1-6
Use the following problem statement to answer questions 1-6.
The project network below shows activity times (in weeks) and their precedence relationships.
[Note]ES= Maximum (EF).EF=ES+t.LF= Minimum (LS). LS = LF - t. Slack =LS-ES. Slack = LF -EF.
1
Multiple Choice
4 points
What is the EF time for activity C? Round to the nearest whole number.
3
10
2
Multiple Choice
4 points
What is the ES time for activity C? Round to the nearest whole number.
6
7
3
Multiple Choice
4 points
What is the LS time for activity E? Round to the nearest whole number.
11
14
 Questions 1-6 Use the following problem statement to answer questions 1-6.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!