Question: Questions 1 - 6 Use the following problem statement to answer questions 1 - 6 . The project network below shows activity times ( in
Questions
Use the following problem statement to answer questions
The project network below shows activity times in weeks and their precedence relationships.
Note Maximum EF Minimum LS LS LF t Slack Slack LF EF
Multiple Choice
points
What is the EF time for activity C Round to the nearest whole number.
Multiple Choice
points
What is the ES time for activity C Round to the nearest whole number.
Multiple Choice
points
What is the LS time for activity E Round to the nearest whole number.