Question: Use the following problem statement to answer questions 1 - 5 . The project network below shows activity times ( in weeks ) and their

Use the following problem statement to answer questions 1-5.
The project network below shows activity times (in weeks) and their precedence relationships.
What is the earliest start (ES) time for activity C?
0
5
21
What is the critical path?
BCDE
BCE
What is the latest finish (LF) time for activity D?
28
12
What is the estimated completion time of the project?
17
30
What is the slack time for activity C?
13
0