Question: Use the following problem statement to answer questions 2 3 - 2 5 . The project network below shows activity times ( in weeks )

Use the following problem statement to answer questions 23-25.
The project network below shows activity times (in weeks) and their precedence relationships. [Note] ES = Maximum (EF).EF=ES+t.LF= Minimum (LS).LS=LF-t. Slack = LS - ES. Slack = LF - EF.
Question 23
6 pts
What is the slack time for activity C?
4
1
2
5