Question: Questions If a plan estimates that 5 , 1 8 4 labor - hours will be expended on a series of related construction activities, and
Questions
If a plan estimates that laborhours will be expended on a series of related
construction activities, and the projected number of construction worker equivalents
expected to perform that activity is personnel working a hour day, what is the
calculated overall duration for those activities? Assume the work is performed
sequentially. Points
a work weeks
b calendar days
c work weeks
d work days