If a plan estimates that 5,184 labor-hours will be expended on a series of related
construction activities, and the projected number of construction worker equivalents
expected to perform that activity is 12 personnel working a 12-hour day, what is the
calculated overall duration for those activities? Assume the work is performed
sequentially. (3 Points)
a)6 work weeks
b)35 calendar days
c)5 work weeks
d)36 work days