Question: Quotable manufactures a removable disk for PC s . There are four major stages in its manufacturing. The first stage is coating of disks. Coating
Quotable manufactures a removable disk for PCs There are four major stages in its manufacturing. The first stage is coating of disks. Coating is done by an automated machine that can run hoursday It produces at the rate of diskshour The second stage is assembly of the disk into the case. Assembly takes the average worker minutesdisk There
are workers at this stage. The third stage is testing, which catches defects from the coating operation. Each testing machine takes minutes to test a disk. There are machines and enough operators to keep these machines busy if necessary. The fourth stage is labeling the disk. Each worker here can do disksminute NOT minutesdisk There are workers who do this task.
Assume the workforce completes full hours of work each day, and stages through run hoursday Stage runs for hours per day. Demand is disksday
Assume all rates and times are deterministic no variability in demand or production Assume quality, that is testing finds no defects.
a Fill in a table similar to the one below
Stage
Resource
Time minutesdisk
Capacity for one resource diskshour
Capacity for all resources at this stage. disksday
b Explain why there is sufficient capacity to meet demand.
c The manager suggests that assembly and labeling can be combined into a single step, so that this single step now has workers. The total raw processing time for one disk does not change. Assume testing is done after this new combined step. Is a reduction in fulltime workforce possible? Show your work.
d Assume that exactly of the disks from a days production of the coating stage are defective and has to be thrown. Assume testing is done after the new
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock