Question: Radiant Systems allocate manufacturing overhead based on machine hours. Each connector should require 10 machine hours. According to the static budget Radiant expected to incur
Radiant Systems allocate manufacturing overhead based on machine hours. Each connector should require 10 machine hours. According to the static budget Radiant expected to incur the following (Click the icon to view the static budget information) During August, Radiant actually used 600 machine hours to make 125 connectors and spent $5,700 in variable manufacturing costs and 59,100 in foced manufacturing overhead costs Calculate the variable overhead cost varlance for Radiant Data table O A $6,013 F OB. $1950 U OC. $4,063 F D. $2 113 F 800 machine hours per month (80 connectors 10 machine hours per connector) $5.000 in variable manufacturing overhead costs $5550 in fixed manufacturing overhead costs Print Done