Question: Rationale The previous MPS plan included a receipt that was required in period 1 . It has been carried over and is shown in the

Rationale
The previous MPS plan included a receipt that was required in period 1. It has been carried over and is shown in the grid.
PAB for periods 1 and 2 will use actual orders for the calculation, as they are before the demand time fence. In period 3, the
actual orders are equal to the period 2PAB, with a resulting PAB of zero in period 3. This is less than safety stock and
requires an MPS receipt to be scheduled in period 3.
For this question, use the following example for an MTS environment. Note that the MPS receipt scheduled in period 1 was
carried over from a previous plan.
On hand: 20
Planning time fence: 7
Lot size: 40
Safety stock: 5
Demand time fence: 2
Given the above information, in which period will the first MPS receipt occur after the demand time fence?
Answers
Period 1
Can't tell
Period 3
Period 2
 Rationale The previous MPS plan included a receipt that was required

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!