Question: Rationale The previous MPS plan included a receipt that was required in period 1 . It has been carried over and is shown in the
Rationale
The previous MPS plan included a receipt that was required in period It has been carried over and is shown in the grid.
PAB for periods and will use actual orders for the calculation, as they are before the demand time fence. In period the
actual orders are equal to the period PAB, with a resulting PAB of zero in period This is less than safety stock and
requires an MPS receipt to be scheduled in period
For this question, use the following example for an MTS environment. Note that the MPS receipt scheduled in period was
carried over from a previous plan.
On hand:
Planning time fence:
Lot size:
Safety stock:
Demand time fence:
Given the above information, in which period will the first MPS receipt occur after the demand time fence?
Answers
Period
Can't tell
Period
Period
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock