Question: Refer to the activity network table below. Using MS Project software, produce a Resource Usage sheet, identifying the total number of hours and daily commitments

Refer to the activity network table below. Using MS Project software, produce a Resource
Usage sheet, identifying the total number of hours and daily commitments of each project team
member.
Activity Duration Predecessors Resource Assigned
A. User survey 4 None Gail Wilkins
B. Coding 12 A Tom Hodges
C. Debug 5 B Wilson Pitts
D. Design interface 6 A, C Sue Ryan
E. Develop training 5 D Reed Taylor