Question: Refer to the table and conditions below to develop a complete cash flow chart. Note that the project will be completed in 7 months. Conditions

Refer to the table and conditions below to develop a complete cash flow chart.
Note that the project will be completed in 7 months.
Conditions of Cash Flow:
There is a two-month time lag in the schedule of monthly payment from the owner to the general contractor.
The owner hold 12% of monthly payment as retention money, but the general contractor cannot hold any retention from subcontract payment.
Retention will be released over two months in equal amount (one half per month) after the completion of job.
Monthly subcontract cost is 70% of value per month, and no retention will be held by the contractor.
There is a one-month time lag in the schedule of monthly payment from the general contractor to the subcontractors.
Fill out the green cells.
 Refer to the table and conditions below to develop a complete

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!