Question: Relevant information for a project consisting of activities A, B, ..., H is provided in the table below and the project network is provided. Immediate

Relevant information for a project consisting of
Relevant information for a project consisting of activities A, B, ..., H is provided in the table below and the project network is provided. Immediate Activity Time in weeks Predecessors A N/A 5 B A A 6 D B, C 7 E 7 F B 7 G D, E 5 H F, G 3 What is slack time for activity B