REM Manufacturing Co. Ltd. is designing an assembly line for the new product line. They want to produce 600 items in a day. They plan to operate the facility 8 hours a day. The design team gathered tasks, processing times, and sequence requirements shown below for optimization of the assembly line. No cellular layout will be used.
Tasks
Processing time (sec.)
Immediate Predecessor(s)
A
20
None
B
25
A
C
15
A
D
30
B
E
20
D
F
35
D
G
30
E
H
27
C, F
I
15
G, H