Question: Reorder Point Ordering: Average lead time ( ? b a r ( L T ) ) is 2 0 days, with a std . dev.

Reorder Point Ordering: Average lead time (?bar(LT)) is 20 days, with a std. dev. (LT) of 6 days. Daily demand (d) is 50 units (constant). Find safety stock (SS) and reorder point (ROP) for z=2.
 Reorder Point Ordering: Average lead time (?bar(LT)) is 20 days, with