Question: Reorder Point Ordering: Average lead time is 30 days, with a std. dev. of 20 days. Daily demand is 60 units. Find demand during lead

Reorder Point Ordering: Average lead time is 30 days, with a std. dev. of 20 days. Daily demand is 60 units. Find demand during lead time (), safety stock () and the reorder point () for .