Question: ! Required information The following data is provided for a PPP project. To the People Benefits Disbenefits $115,000 per year beginning now $60,000 per

! Required information The following data is provided for a PPP project. To the People Benefits Disbenefits $115,000 per year beginning now $60,000 per year Cost Savings Calculate the modified benefit/cost ratios using an interest rate of 10% per year and an infinite project period. The modified B/C ratio is .55 To the Government $1.8 million now and $200,000 every 3 years $105,000 per year