Question: Required information The following data is provided for a PPP project. To the People To the Government Benefits $150,000 per year beginning now Cost $1.8

Required information

The following data is provided for a PPP project.

To the People To the Government
Benefits $150,000 per year beginning now Cost $1.8 million now and $200,000 every 3 years
Disbenefits $65,000 per year Savings $120,000 per year

Calculate the modified benefit/cost ratios using an interest rate of 6% per year and an infinite project period.

The modified B/C ratio is .