Question: Resource Leveling The following information is given: Activity Predecessor Duration (days) Labor Required for activity (per day) A - 4 4 B A 5 3

Resource Leveling

The following information is given:

Activity Predecessor Duration (days) Labor Required for activity (per day)
A - 4 4
B A 5 3
C - 3 5
D - 6 3
E D 4 4
F B,C,E 2 2

a. What is the duration and critical path?

b. If no more than 8 laborers can be working a day at a time, what needs to be done to the schedule?

c. Can the schedule still be completed in the original duration?