Question: Resource Leveling The following information is given: Activity Predecessor Duration (days) Labor Required for activity (per day) A - 4 4 B A 5 3
Resource Leveling
The following information is given:
| Activity | Predecessor | Duration (days) | Labor Required for activity (per day) |
| A | - | 4 | 4 |
| B | A | 5 | 3 |
| C | - | 3 | 5 |
| D | - | 6 | 3 |
| E | D | 4 | 4 |
| F | B,C,E | 2 | 2 |
a. What is the duration and critical path?
b. If no more than 8 laborers can be working a day at a time, what needs to be done to the schedule?
c. Can the schedule still be completed in the original duration?