Question: Review the attached Excel Spreadsheet and complete the assignment.Construct the Network Diagram, as defined by Predecessor and Duration columns Question on excel: 1. How long

Review the attached Excel Spreadsheet and complete the assignment.Construct the Network Diagram, as defined by Predecessor and Duration columns

Question on excel:

1. How long will it take you to complete the garage?

2. If you wanted to shorten the project by 1 day, what activity would you shorten?

Predecessor Duration D1 D2 D3 D4 D5 D6 D7 D8 D9 D10 D11 D12 D13 D14 D15 D16 D17 D18 D19 D20
A Pour Foundation None 3d
B Erect Frame A 4d
C Roof B 4d
D Windows B 1d
E Doors B 1d
F Electrical B 3d
G Rough-in Frame C,D,E,F 2d
H Door Opener E,F 1d
I Paint G,H 2d
J Cleanup I 1d

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!